Communication plan

Purpose. Make communication a plan rather than an afterthought, so that stakeholders learn about change from the project rather than about the project from each other.

Project details​

FieldDetail
Project
Client
Owner
Date

Objectives​

  1. Every stakeholder knows what is changing and why.
  2. Decisions are communicated by the person who made them, to the people affected.
  3. No stakeholder learns about a material change from a third party.
  4. Concerns have a route into the project and a visible response.

Audience matrix​

AudienceWhat they needLevel of detailChannelFrequencyOwner
Executive sponsorOutcome, risk, decisions neededSummarySteering meeting, written updateMonthlyPM
Department headsImpact on their department, timelinesSummary + impactBriefingMonthlyPM
Engineering teamTechnical direction, changes, actionsDetailedStand-up, written notesWeeklyTech lead
Operations / on-callOperational changes, runbooks, alarmsDetailedHandover session, runbook updatesPer changeDevOps lead
SecurityControl changes, findings, risksDetailedSecurity reviewPer changeSecurity lead
All staffWhat is changing and whenHeadlineEmail or town hallAt milestonesSponsor
Customers (if affected)Service changes, windowsHeadlineNoticePer changeAccount owner

Message templates​

Milestone update​

Subject: [Project] — [milestone] complete

What changed: [one or two sentences] What it means for you: [specific impact, or "no action required"] What happens next: [next milestone and date] Questions: [contact]

Change notice​

Subject: Planned change — [system] — [date]

What: [change description] When: [window, with time zone] Impact: [none / degraded / unavailable — and for how long] If something goes wrong: [rollback plan and expected recovery time] Contact during the window: [name, channel]

Risk escalation​

Subject: Risk escalation — [risk] — decision needed by [date]

Situation: [what has happened] Impact if unresolved: [consequence] Options: [option, cost, trade-off] Recommendation: [preferred option and why] Decision needed from: [name] by [date]

Schedule​

DateAudienceMessageOwnerChannelStatus
Kick-off announcedPlanned
Discovery findingsPlanned
Design approvedPlanned
Pilot resultsPlanned
Go-live noticePlanned
Handover completePlanned

Escalation path​

LevelTriggerWhoResponse time
1Delivery blockerProject managerSame day
2Blocker affecting a milestoneSponsor2 working days
3Scope, budget or contractual impactExecutive sponsor5 working days

Feedback channels​

ChannelPurposeOwner
Weekly delivery reviewConcerns raised and answeredPM
Anonymous surveyCulture and readiness feedbackChange lead
Direct escalationIndividual concernsSponsor