Delivery model

A project is confirmed only when its outcomes, scope boundaries, success criteria and responsibilities are written down and agreed. Everything else is a conversation that will be re-litigated later.

Scoping process​

Five stages, each with a named owner and a defined output that feeds the next.

StageOwner (RACI)ActivitiesOutput
1. Needs assessmentSales (R), PM (A), Technical lead (C)Structured questionnaire covering business context, current environment, application components, delivery pain points, compliance needs and target outcomes. Reviewed for completeness by the technical lead.Completed needs assessment
2. Discovery workshopPM (R), Technical lead (A)Current-state architecture, workload inventory, DevOps maturity across source control, IaC, CI/CD, observability and security; constraints; prioritised objectives.Findings, prioritised objectives, constraints
3. Project charterPM (R), Sponsor (A)Executive summary, SMART objectives, business case, in and out of scope, success criteria, KPIs, deliverables, budget, milestones, stakeholders, assumptions, risks.Approved charter
4. Statement of workSales (R), PM (A), Technical lead (C)Target architecture, expected AWS cost, phased plan with effort, deliverables, milestones, out-of-scope list, responsibilities, acceptance criteria, change control, commercial terms.Signed SOW — the scope baseline
5. Kick-offPM (R), Technical lead (C), Client (I)Confirms scope, deliverables, milestones, RACI, communication plan and reporting cadence.Kick-off record and summary

Scoping criteria​

A project is confirmed only when every item below is defined and agreed.

Business objectives
Business drivers and SMART goals, with the success criteria and KPIs that show they were met.
Current state
Existing environment, application components, hosting, data and limitations, documented from assessment and discovery.
Target state
Target AWS architecture, diagrammed, with expected AWS cost estimated per service.
In-scope work
Selected phases and tasks from the standard plan, each with an effort estimate in days.
Out of scope
An explicit list. An empty out-of-scope section is a scope dispute waiting to happen.
Deliverables
Tangible, verifiable outputs with acceptance criteria.
Milestones
Dates and the decision or artefact each milestone produces.
Responsibilities
RACI across Qbits and the customer for every scoping and delivery activity.
Assumptions and constraints
Access, availability of customer staff, existing tooling, procurement lead times, regulatory constraints.
Acceptance criteria
How the customer will determine that a deliverable is complete.
Change control
The procedure that applies after signature.

Standard technical plan​

Work is selected from a nine-phase menu, each phase with a defined set of tasks and an effort estimate. Not every engagement needs every phase; the menu makes the selection explicit and the estimate comparable.

PhaseContent
1. Planning and preparationRequirements confirmation, access, tooling, project setup
2. AWS account setupOrganisation, accounts, identity, guardrails
3. Network fabric and baseline IaCVPC, subnets, routing, baseline Terraform
4. Migration executionWorkload migration, data transfer, cutover
5. DevOps practices and system designPipelines, IaC modules, environment topology
6. Security and observabilityControls, detection, monitoring, dashboards
7. TestingFunctional, load, resilience, security
8. Knowledge transfer and handoverDocumentation, training, game day
9. Project closureAcceptance, review, retrospective, closure report

Project management​

A dedicated project manager is assigned to every engagement. The PM owns:

  • The plan, the critical path and the risk register.
  • Status reporting and the communication plan.
  • Change control and the change register.
  • Stakeholder management and escalation.
  • Acceptance and closure.

Roles​

RoleResponsibility
Project sponsor (customer)Owns the outcome; removes organisational blockers; approves scope and budget changes
Project managerPlan, risk, change, communication, reporting
Technical leadArchitecture decisions, technical quality, delivery risk
Delivery engineersImplementation against the standards
Security leadSecurity review, control design, incident readiness
Customer technical ownerAccess, environment knowledge, acceptance
Change managerChange register, CAB coordination

Reporting cadence​

ReportFrequencyContent
Stand-upDaily or weeklyProgress, blockers, next steps
Status reportWeeklyRAG status, milestones, risks, decisions needed
Steering updateMonthlyOutcome progress, budget, escalations
Milestone reviewPer milestoneDeliverables, acceptance, KPI movement
Closure reportEndOutcome against objectives, lessons, handover state

RACI​

Every activity has exactly one accountable owner. A RACI with several A's is not a RACI; it is a disagreement that has not been resolved.

ActivityQbits PMQbits Tech LeadCustomer SponsorCustomer Tech
Scope definitionACAC
ArchitectureCAIC
Environment accessRCAR
ImplementationRAIC
Security reviewCRIA
AcceptanceRCAR
Change approvalRCAC