Risk management

A risk register is useful when it changes decisions. A register of generic risks that nobody reads is a compliance artefact, not a control.

Process​

Identify → Assess (impact × likelihood) → Respond → Assign → Review → Close

Likelihood​

LevelDescriptionProbabilityScore
5Near certainty81–99%5
4Highly likely61–80%4
3Likely41–60%3
2Low likelihood21–40%2
1Not likely0–20%1

Impact​

LevelDescription
5Critical — outage, data loss, regulatory breach, project failure
4Significant — major delay, material cost, customer-visible degradation
3Moderate — delay to a milestone, rework, additional cost
2Minor — inconvenience, contained rework
1Negligible — no material effect

Rating matrix​

Likelihood ↓ / Impact →1 Negligible2 Minor3 Moderate4 Significant5 Critical
5 Near certainty5 Medium10 High15 Extreme20 Extreme25 Extreme
4 Highly likely4 Low8 Medium12 High16 Extreme20 Extreme
3 Likely3 Low6 Medium9 Medium12 High15 Extreme
2 Low2 Low4 Low6 Medium8 Medium10 High
1 Not likely1 Low2 Low3 Low4 Low5 Medium
BandScoreAction
Low1–4Accept; monitor
Medium5–9Mitigate as low as reasonably practicable
High10–16Mitigate; named owner; reviewed weekly
Extreme17–25Escalate to sponsor; consider pausing the affected work

Categories​

CategoryTypical risks
TechnicalData loss during migration, incompatible legacy dependencies, performance shortfall
ScheduleAccess delays, customer availability, procurement lead time
ScopeUndiscovered systems, requirements changing mid-delivery
CostCloud spend above estimate, migration egress, unplanned licences
SecurityCredential exposure, misconfiguration, insecure legacy components
ComplianceData residency, audit evidence gaps, regulatory change
OrganisationalSponsor departure, resistance from an affected department, key-person dependency
SupplierAWS service limits, third-party integration failure, vendor support

Register​

IDRiskCategoryImpactLikelihoodScoreResponseOwnerStatus
R-01Data loss during migrationTechnical4312 HighRehearsed migration, DMS with validation, pre-cutover snapshotData leadOpen
R-02Account access delayedSchedule3412 HighAccess request raised in week 1; sponsor escalation pathPMOpen
R-03Cost exceeds estimateCost339 MediumMonthly cost review; budget alarms; right-sizing checkpointCloud leadOpen

Responses​

StrategyWhen
AvoidChange the plan so the risk no longer exists
ReduceLower likelihood or impact through a control
TransferMove the consequence — insurance, contractual terms, vendor SLA
AcceptAcknowledge and monitor; appropriate for Low risks and where mitigation costs more than the exposure

Every Medium or higher risk has a response, an owner and a date. "Monitor" is a response only for Low risks.

Review cadence​

ForumFrequencyContent
Delivery stand-upWeeklyNew risks, changes to High risks, blockers
Risk reviewFortnightlyFull register; score changes; mitigation progress
SteeringMonthlyExtreme and High risks; escalations; acceptance decisions

Risk to delivery, not just risk in delivery​

The assessment also covers the risk of the transformation itself:

  • Organisational resistance that delays adoption.
  • A pilot that succeeds technically but does not generalise.
  • A sponsor who leaves mid-programme.
  • A security finding that pauses migration.
  • A dependency on one engineer's knowledge.

These belong in the register alongside the technical risks. They are the ones most likely to affect the outcome.