Change management

Change management exists so that a change to scope, schedule, architecture or budget is a decision rather than a surprise. Every change is written down, assessed before approval, and reviewed after delivery.

The standard. A process to document, assess, approve and review changes to project scope, schedule and cost.

Principles​

  1. Every change is written down. Verbal and chat requests are captured in a change request before any work begins.
  2. Every change is assessed before approval. Impact on scope, timeline, budget, resources, architecture and security is evaluated by the delivery team.
  3. Every change is approved by the right people. Approval authority sits with a Change Advisory Board that includes both Qbits and customer stakeholders.
  4. Every change is traceable. A change register is the single auditable record.
  5. Every change is reviewed after delivery. A post-change review captures lessons and feeds back into the process.

Triggers​

A change may originate from:

  • The customer — new requirement, priority shift, constraint.
  • The delivery team — a discovered dependency, an architecture correction.
  • External factors — an AWS service change, a security finding, a regulatory requirement, a supplier issue.

All three enter the same process.

Stages​

StagePurposeArtefact
1. Change requestCapture the change, the rationale and the requesterChange Request Form
2. Impact assessmentEvaluate technical, schedule, cost, resource and risk implicationsCompleted impact section
3. CAB review and approvalApprove, reject, defer or modifyCAB minutes; decision in the register
4. Implementation planningDefine tasks, owners, timeline, rollback and communicationChange Implementation Plan
5. ImplementationExecute under control, with progress reportingUpdated plan, backlog and deliverables
6. Post-change reviewVerify outcome, capture lessons, closePost-Change Review; register closed

1. Change request​

The Change Request Form captures:

  • Unique ID, date raised, requester, affected project.
  • Nature: scope, timeline, budget, deliverables, architecture, or a combination.
  • Rationale and business or technical driver.
  • Preliminary impact on timeline, budget, resources and scope.
  • Supporting documentation.

2. Impact assessment​

The Change Manager decides whether a full feasibility study is required, based on:

  • The number of options presented.
  • The complexity of the options.
  • The scale of the solution proposed.

A full study covers:

  • Change requirements.
  • Options analysis — cost, benefit, risk, issues.
  • Impact assessment.
  • Recommendation and implementation plan.

3. Approval​

The CAB selects one outcome:

  • Reject.
  • Request more information.
  • Approve as requested.
  • Approve subject to conditions.

The decision, the conditions and the rationale are recorded in the register.

4. Implementation planning​

ElementContent
TasksWhat will be done
OwnersWho is accountable for each
TimelineStart, milestones, completion
RollbackHow to reverse if it fails
CommunicationWho is told, when, how
VerificationHow completion will be confirmed

5. Implementation​

Progress is reported at the normal delivery cadence. A change that starts to exceed its assessment triggers a re-assessment rather than an ad hoc extension.

6. Post-change review​

  • Did the change achieve its intended outcome?
  • Did it cost what was estimated, in effort and money?
  • Did it affect anything not identified in the impact assessment?
  • What should change in the process next time?

Change register​

FieldContent
IDCR-001, CR-002 …
Date raised
Requester
Description
TypeScope, schedule, budget, architecture, deliverable
Impact
DecisionApproved, rejected, deferred, conditional
Conditions
Owner
Implementation dates
StatusOpen, in progress, complete, closed
Post-change reviewDate and findings

Thresholds​

Not every adjustment needs the full CAB. Define thresholds in the SOW:

ChangeApproval
Within agreed tolerance on effort and scheduleProject manager
Exceeds tolerance; affects a milestoneCAB
Affects contract scope, price or acceptance criteriaCAB plus sponsor, with a contract amendment

Agreeing the thresholds up front prevents both bureaucracy on small changes and drift on large ones.