Change request

Purpose. Capture a proposed change and its impact before any work begins. Verbal and chat requests are transcribed here.

Request​

FieldDetail
Change request IDCR-
Date raised
Raised by
Affected project
Contact

Nature of the change​

  • Scope
  • Schedule / timeline
  • Budget
  • Deliverables
  • Architecture
  • Combination:

Description​

What is being requested? Be specific about what changes and what does not.

Rationale​

What is the business or technical driver? What happens if the change is not made?

Preliminary impact​

DimensionImpactEffort
Scope
Schedule
Budget
Resources
Architecture
Security / compliance
Risk

Options​

OptionDescriptionCostBenefitRisk
A
B
Do nothing

Recommendation​

Preferred option, and why.

Supporting documentation​

DocumentLink

Impact assessment (completed by the delivery team)​

FieldDetail
Assessed by
Date
Feasibility study required?Yes / No — reason
Technical impact
Schedule impact
Cost impact
Resource impact
Security impact
Risk to delivery
Mitigation

Decision (completed by the CAB)​

FieldDetail
DecisionApproved / Rejected / Deferred / Approved with conditions
Conditions
Rationale
Decided by
Date
Register updatedYes / No

Implementation plan​

TaskOwnerStartEnd

Rollback plan:

Communication:

Verification:

Post-change review​

FieldDetail
Was the outcome achieved?
Actual effort vs estimate
Unidentified impacts
Lessons for the process
Closed by / date