Change advisory board

The CAB reviews requests for change that affect the operational environment. Its job is to make a decision with enough information to defend it, not to add a meeting between a decision and its implementation.

Purpose​

Assess every request for change for technical, operational, security, compliance and quality impact before it is implemented.

Core members​

Members are appointed by role; the individual changes without the seat changing.

RoleContributionDecision rights
CAB chair (technical executive)Runs the meeting, sets the agenda, breaks tiesFinal decision on a tie
Technical leadTechnical feasibility and implementation planningFinal technical approval
Program managerOperational impact and alignment with infrastructureVote on operational and infrastructure changes
Head of securitySecurity implications and control complianceVote on security-affecting changes
Compliance officerLegal, regulatory and policy conformanceVote where compliance is affected
Senior developer representativeDevelopment impactAdvisory
DevOps leadDelivery and operations impactAdvisory
QA managerTesting and quality impactAdvisory
Network architectNetwork architecture and performance impactAdvisory

Advisory members​

Invited per change, without a vote:

RoleContribution
Business ownerCustomer-facing impact
Project managerEffect on features and timelines
Systems administratorSystem configuration impact
Database administratorData integrity and database risk
Application supportOperational impact on running services

Decision model​

A change is approved when the voting members reach consensus. Where consensus is not reached:

  1. The chair summarises the disagreement and its basis.
  2. The security or compliance member may hold the change if the concern is a control obligation. This is not veto by seniority; it is a legal constraint.
  3. The chair decides, and the decision and dissent are recorded.

Recording dissent matters: if the change fails, the record shows what was considered.

Meeting rhythm​

MeetingFrequencyContent
Standard change reviewWeeklyOpen requests, impact assessments, decisions
Emergency CABOn demandUrgent changes with a compressed assessment
Post-change reviewMonthlyOutcomes of implemented changes

Agenda​

  1. Review of previous actions.
  2. Open requests in order of risk.
  3. Impact assessment presentation by the requester.
  4. Questions and decision.
  5. Emergency changes since the last meeting, for retrospective review.
  6. Register status and ageing.

Change classes​

ClassExamplesRoute
StandardPre-approved, low risk, repeatable — routine deployment through the pipelineAutomated approval; recorded
NormalPlanned change with assessmentCAB review
EmergencyIncident remediation, security responseEmergency CAB or delegated authority, reviewed afterwards

The standard class exists so that routine work does not consume CAB time. If a standard change starts appearing in incidents, its classification is wrong.

Information the CAB needs​

A request without this information is deferred, not guessed at:

  • What changes, and why.
  • Which systems and customers are affected.
  • What happens during implementation — downtime, degraded performance, none.
  • Rollback plan and its time to execute.
  • Test evidence — what was verified, and where.
  • Security and compliance impact.
  • Communication already sent, or planned.
  • Who will be on hand during and after.

Operating rules​

  1. Decisions are made in the meeting. A request that is "still being reviewed" for three cycles is a decision to delay — record it as such.
  2. Emergency is not bypass. An emergency change is approved by a named delegate, implemented under the same rigour, and reviewed at the next CAB.
  3. Repeat changes get a standard. A change that recurs monthly should become a standard or an automation.
  4. The register is the record. Minutes that are not in the register are not evidence.
  5. Post-incident, not post-blame. The post-change review asks what the process missed, not who missed it.