Customer acceptance

Acceptance is a defined event with defined evidence. Satisfaction is measured along the way, at milestones, so that a problem is corrected before closure rather than documented after it.

The standard. A defined acceptance process with clear handoff responsibilities and acceptance criteria, plus satisfaction checkpoints at each project milestone.

Acceptance criteria​

Defined in the statement of work before delivery begins:

CriterionEvidence
Deliverables deliveredEach item accessible and matching its description
Functional testing completeTest results recorded and reviewed
User acceptance testing completeUAT scenarios passed within the acceptance window
Training deliveredAttendance and recordings
Documentation handed overCustomer review record
Operational readinessDrill results: deploy, rollback, restore

Acceptance process​

  1. Readiness review The delivery team confirms every deliverable against its criteria and assembles the evidence pack.

  2. Customer review The customer reviews deliverables and evidence within the agreed window and raises any gaps.

  3. Correction Gaps are corrected within an agreed period. A correction that changes scope becomes a change request.

  4. Verification session The customer performs the key operations unaided: deploy, roll back, restore.

  5. Formal sign-off The acceptance record is signed by the customer's authorised representative.

  6. Closure Closure report, retrospective, and transition to support.

When the customer does not respond​

The SOW defines the rule. A common and defensible default: if no issues are raised within the review window, the deliverables are deemed accepted, and the record states that the window elapsed. Silence is not the same as approval, so the rule is written down rather than assumed.

Satisfaction checkpoints​

Measured at every milestone, not only at the end.

CheckpointWhenInstrument
Kick-offAfter scope is confirmedShort pulse survey
Discovery completeAfter workshops and interviewsStructured feedback
Design approvedAfter architecture sign-offPulse survey
Pilot completeAfter the pilot decisionPilot feedback report
UAT completeBefore productionSatisfaction survey
HandoverAt acceptancePost-delivery questionnaire
Post-engagement30–90 days laterRelationship survey

Questions that produce useful answers​

  • Is the work meeting your expectations? Where does it fall short?
  • Do you understand what is being built and why?
  • Are you getting the information you need, at the frequency you need it?
  • Is the team responsive when you raise an issue?
  • Would you recommend working with us? Why or why not?

A satisfaction score without a reason is not actionable. Always ask why.

Responding to feedback​

SignalResponse
Score drops at a checkpointDiscuss at the next steering meeting; agree corrective action
Repeated concern across customersProcess change, not a project change
Individual escalationDirect conversation with the sponsor within 48 hours
Positive but low-confidenceAsk what would need to change for a higher score

Feedback is closed with the customer — they are told what changed as a result. Otherwise the next survey measures their cynicism, not their satisfaction.

Closure​

ArtefactContent
Acceptance recordCriteria, evidence, sign-off
Project completion reportOutcomes against objectives, KPIs, deviations
Post-implementation reviewWhat worked, what did not, what to change
Final satisfaction resultScore, verbatim feedback, actions taken
Handover packDocumentation, runbooks, training recordings
Support transitionWho supports what, from when, how to escalate